Key dates.

(Updated March 10, 2016) 

March
Capital campaign completed

April

  • Official consideration by The Town of Davidson Design Review Board
  • Selection of contractor for design development work with architect and engineer

May
Begin design development phase

July

  • Receive design development pricing from contractor 
  • Begin construction drawing phase 

August

  • Early submit for site permit review
  • Specs from engineers 

September

  • All drawings complete
  • Town of Davidson Building Permit Review 

October

  • Pricing from general contractor
  • Metro District of the Western North Carolina Annual Conference - Final approval from Committee on Location and Building 
  • Final vote by the congregation to proceed

November

  • Plan submitted to Mecklenburg County for building permit
  • Construction agreements signed

January 2017
Construction begins